Sewer Construction Update

Thank you for all of your help and assistance with the project.  So far so good.  We’re in the home stretch.

The attached map shows the actual sewer main (in blue) that is completed and the remaining that is in red and the dates of completion.

Please note that there will also be sewer connection installation crews on 6A until 5/2, rte 28 until 5/7 and Main St. until 5/10.  They will perform the last temp. trench patch for the season on 5/11.

Please note that all dates could change with weather, etc.  If all goes well Revoli will be done 2 weeks ahead of schedule, which is great news.

Final trench paving will be in September.