Construction Update: Wednesday February 28th

DOWNTOWN CONSTRUCTION UPDATE:
3/5 Monday – Pave drive adjacent to Bill’s Sunoco to allow traffic to flow through Post Office Square
3/6 Tuesday – Begin Sewer installation on Main St. in front of Snow Library. Library parking will be most likely closed on 3/6 and 3/7. Library parking will be provided across the street within PO Square as shown.
Library parking will be most likely interrupted again for one day, tentatively again on 3/15.
3/7 Wednesday – Second crew begins sewer installation on Main St. adjacent to Cummings Rd.
We will bring you more updates as they become available.