Construction Update: Thursday March 8

3/12/18 Monday – Begin Sewer installation on Main St. in front of Library. Library parking will be most likely closed on 3/12 and 3/13. Library parking will be provided across the street within PO Square as previously shown.

Library parking will be most likely interrupted again for one day, tentatively again on or about 3/21.

3/12/18 Monday – Second crew begins sewer installation on Main St. adjacent to Cummings Rd. 

Please bear in mind this schedule may change due to unforeseen circumstances and/or weather. 

We will bring you more updates as they become available.