Two-Week Look Ahead Starting January 4, 2021

Every week the construction contractors for Contract No. 2019-01 – Downtown Area Wastewater Treatment Facility and Effluent Disposal, Daniel O’Connell’s Sons, Inc. and Contract No. 2019-02 – Downtown Area Collection System and Pumping Stations, Robert B. Our Co., Inc. provide a “two-week look ahead” that summarizes anticipated construction activity in the planned project area.

Contract No. 2019-01 – Downtown Area Wastewater Treatment Facility and Effluent Disposal

During the next two weeks, construction crews and detours are scheduled to be at the following locations:

  • 29 Overland Way: Expect construction traffic and equipment to be entering and exiting at Bay Ridge Lane.  Work includes formwork, rebar installation, placing concrete for base lab, and installing perimeter fence.
  • 32 Lots Hollow Road: Expect construction traffic and equipment to be entering and exiting at Lots Hollow Road.  Work includes finishing concrete and forming the supported deck of effluent disposal distribution box.

Contract No. 2019-02 – Downtown Area Collection System and Pumping Stations Area

During the next two weeks construction crews and detours are scheduled to be at the following locations:

  • Main Line Crew 1: West Road between Old Colony Way and Route 6A moving south toward Route 6A installing force main sewer, gravity sewer, service tees, and fiber optic conduit. 
  • Testing Crew: Old Colony Way and West Road pressure testing gravity pipe and vacuum testing manholes.
  • Traffic Delays/Detours: Traffic detours are scheduled for West Road weekdays from 7AM to 4PM. West Road is closed to through traffic, but access to West Road will be allowed to residents and local businesses by either Old Colony Way or Route 6A. Please check with the detail officer located at either side of West Road for best access. See detour plans on the “Construction Activities and Detours” webpage.

The plans, system map and additional information are available on the Town’s website.

https://www.town.orleans.ma.us/wastewater-infrastructure/phase-1-downtown-area

Baker-Polito Administration Announces $668 Million Small Business Relief Package
7 Lower Cape Based Non-Profits Collaborate to Better Serve the Community
Menu