Two-Week Look Ahead Starting September 28, 2020
Every week the construction contractors for Contract No. 2019-01 – Downtown Area Wastewater Treatment Facility and Effluent Disposal, Daniel O’Connell’s Sons, Inc. and Contract No. 2019-02 – Downtown Area Collection System and Pumping Stations, Robert B. Our Co., Inc. provide a “two-week look ahead” that summarizes anticipated construction activity in the planned project area.
Contract No. 2019-01 – Downtown Area Wastewater Treatment Facility and Effluent Disposal
During the next two weeks, construction crews and detours are scheduled to be at the following locations:
- 29 Overland Way: Expect construction traffic and equipment to be entering and exiting at Bay Ridge Lane. Work includes clearing vegetation, layout for excavation, site tree clearing, and mobilizing equipment and materials.
- 32 Lots Hollow Road: Expect construction traffic and equipment to be entering and exiting at Lots Hollow Road. Work includes tagging approved trees for removal and clearing and grubbing of the site area
Contract No. 2019-02 – Downtown Area Collection System and Pumping Stations Area
Starting the week of October 5, 2020, construction crews and detours are scheduled to be at the following locations:
- Main Line Crew 1: #89 Old Colony Way to #18 Old Colony Way gravity sewer installation
- Main Line Crew 2: #89 Old Colony Way to #18 Old Colony Way replacing 8” water main
- Traffic Delays/Detours: Traffic delays may occur on Old Colony Way and West Road. In addition, traffic detours are scheduled for Old Colony Road, see detour plan on “Construction Activities and Detours” webpage
The plans, system map and additional information are available here. For questions please contact: Martin “Reggie” Donoghue, P.E.:Telephone: 508-833-6967
Click here to email Reggie Donoghue
Please note that this is a projected schedule and is subject to adjustment based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing pipe and manhole testing, interior manhole work, raising manhole covers in preparation for paving, paving and performing general cleanup at various locations throughout the project area.